Hello everyone,
I am unsure if this is the right forum to ask this as there is a lot of details and requirements in it.
I am working to create a capacity planning database (I'm not set on Excel being the right software). A capacity plan takes the start dates of a product, adds the standard processing times, determines if the variables are met for machine capacity, and ensure that the appropriate human hours is not over whelmed.
This requires a lot of data to be used but I am hoping it is possible. Attached is a sample document of our standard process times for anonymous projects. I need to be able to type in a new contract and all of the capacity tables automatically update and the Gantt chart is a nice to have, but not required.
I hope this helps, but I am sure there will plenty of questions, feel free to reach out.
Contract Data and Standard Production Times:
Requirements per program per machine:
Available Capacity of Machinery by hour:
Steps requiring which machine type:
Gantt Chart (would be an awesome addition that updates automatically if anything changes in the standards table or new contracts are added):
I am unsure if this is the right forum to ask this as there is a lot of details and requirements in it.
I am working to create a capacity planning database (I'm not set on Excel being the right software). A capacity plan takes the start dates of a product, adds the standard processing times, determines if the variables are met for machine capacity, and ensure that the appropriate human hours is not over whelmed.
This requires a lot of data to be used but I am hoping it is possible. Attached is a sample document of our standard process times for anonymous projects. I need to be able to type in a new contract and all of the capacity tables automatically update and the Gantt chart is a nice to have, but not required.
I hope this helps, but I am sure there will plenty of questions, feel free to reach out.
Contract Data and Standard Production Times:
Requirements per program per machine:
Available Capacity of Machinery by hour:
Steps requiring which machine type:
Gantt Chart (would be an awesome addition that updates automatically if anything changes in the standards table or new contracts are added):