helmi_jusuf
New Member
- Joined
- Jun 7, 2015
- Messages
- 1
Hi... i am new comer here. It's a nice forum 
I want to determine end date of job based on start date and fix duration but with some criteria
i.e for some simulation needed :
Task 1
Start Date : 06/05/2015 08:00 am
Fix Duration : 12 hrs
End Date : formula ??? (should be 06/06/2015 12:00 pm - exclude rest time & working time stop at 5.00 pm jump to next day)
Task 2
Start Date : 06/05/2015 08:00 am
Fix Duration : 9 hrs
End Date : formula ??? (should be 06/06/2015 09:00 am - exclude rest time & working time stop at 5.00 pm jump to next day)
Task 3
Start Date : 06/05/2015 09:00 am
Fix Duration : 36 hrs
End Date : formula ??? (should be 06/09/2015 01:00 pm - exclude rest time & working time stop at 5.00 pm jump to next day)
Criteria :
Work start at 08:00 am
Work end at 5:00 pm
Lunch time 1 hour start at 12:00 pm
Can anyone help me please
I want to determine end date of job based on start date and fix duration but with some criteria
i.e for some simulation needed :
Task 1
Start Date : 06/05/2015 08:00 am
Fix Duration : 12 hrs
End Date : formula ??? (should be 06/06/2015 12:00 pm - exclude rest time & working time stop at 5.00 pm jump to next day)
Task 2
Start Date : 06/05/2015 08:00 am
Fix Duration : 9 hrs
End Date : formula ??? (should be 06/06/2015 09:00 am - exclude rest time & working time stop at 5.00 pm jump to next day)
Task 3
Start Date : 06/05/2015 09:00 am
Fix Duration : 36 hrs
End Date : formula ??? (should be 06/09/2015 01:00 pm - exclude rest time & working time stop at 5.00 pm jump to next day)
Criteria :
Work start at 08:00 am
Work end at 5:00 pm
Lunch time 1 hour start at 12:00 pm
Can anyone help me please