How to Check a Series of Dates Between Two Dates

dineshtendulkar

Board Regular
Joined
Apr 18, 2011
Messages
53
Description Quantity Start Date Finish Date Jan-10 Feb-10
1 2 3 4 1 2 3 4
Excavation 100 05-01-10 14-01-10 30 70

88634e5225.jpg


Hi friends,

I am having an excel spreadsheet as shown above. I have splitted every month into 4 weeks..
1 - 7 = First Week
8-14 = Second Week
15 - 21 = Third Week
22 - 28, 30 or 31 = Fourth Week

What I need now is to Split-up the Quantity as per the Start Date and Finish Date as shown above.

I badly need this formula.. Searched in google I cant able get it. Any Experts Please Help Me

Additional Information

For Example, If i am doing Excavation Activity and if its quantity is 100, the start date is 05-Jan-2010 and Finish Date is 14-Jan-2010

Here we are considering 1-7th of Every month as First Week, but the activity starts on 5th January 2010, So in the first week we have the duration of 3 days and it ends on 14th January 2010, so the second week has the duration of 7 days, so the total duration is 10 days, it should divide the quantity as Total Quantity/total duration and should split the total quantity into weekwise distribution. In this example, for first week 3 days duration so in the first week it should fill (100/10)*3 and in the second week the duration is 7 days and so it should fill as (100/10)*7.

Also you should consider that we are everymonth into 4 weeks. For February month, the last
week will have a duration of 7 days, whereas January, March, May, July, August, October, December will have a duration of 10 days in the last week and April, June, September, November will have a duration of 9 days.

Consider other examples such as,

For example, the total quantity of concrete is 500 and the start date is 22-January-2010 and its finish date is 4-April-2010.

Then it should split the quantity as follows,

January 4th Week = 68.49315
February 1st Week = 47.94521
February 2nd Week = 47.94521
February 3rd Week = 47.94521
February 4th Week = 47.94521
March 1st Week = 47.94521
March 2nd Week = 47.94521
March 3rd Week = 47.94521
March 4th Week = 68.49315
April 1st Week = 27.39726

I think now you better understood my question, I am waiting for your reply boss....
 

Excel Facts

Copy formula down without changing references
If you have =SUM(F2:F49) in F50; type Alt+' in F51 to copy =SUM(F2:F49) to F51, leaving the formula in edit mode. Change SUM to COUNT.
Hello Dinesh,

Firstly define a name EndDay. On Refers to enter this

={0,0;1,3;2,0;3,3;4,2;5,3;6,2;7,3;8,3;9,2;10,3;11,2;12,3}

Then, F3 copy across & down.

=($C3/($E3-$D3+1))*MAX(0,MIN($E3,DATE(YEAR($F$1),INT((COLUMNS($F3:F3)-1)/4)+1,F$2*7)+((F$2=4)*LOOKUP(INT((COLUMNS($F3:F3)-1)/4)+1,EndDay)))-MAX(0,$D3,DATE(YEAR($F$1),INT((COLUMNS($F3:F3)-1)/4)+1,F$2*7-6))+1)

If you don't want to see zero's use the custom format

Code:
0.00;;;

Of course will have a more elegant ways.
 
Upvote 0
Dear Mr. Haseeb

Could you please send me the excel file to dineshtendulkar@gmail.com

How can i define a name Endday and in which cell i should define.

Where i should copy the formula..Please give a detail explanation plz..

Thanks for your reply..

Regards,
Sathish Justin
 
Upvote 0
Dear Mr. Haseeb,

Could you please explain a little about the formula, and why u used that Endday name and what does it mean

Sathish Justin
 
Upvote 0
Dear Mr. Haseeb,

This Formula Works Great, except for the leap years. Could you please adopt the same formula considering the leap year. I will be grateful to you if you give me this.

You have reduced my work with one formula. Thanks man. You are really a genius.

Regards,
Sathish Justin
 
Upvote 0
Glad to hear. It works.

OK, change the EndDay array to;

={0,0;28,0;29,1;30,2;31,3}

Then,

=($C3/($E3-$D3+1))*MAX(0,MIN($E3,DATE(YEAR($F$1),INT((COLUMNS($F3:F3)-1)/4)+1,F$2*7)+((F$2=4)*LOOKUP(DAY(DATE(YEAR($F$1),INT((COLUMNS($F3:F3)-1)/4)+2,0)),EndDay)))-MAX(0,$D3,DATE(YEAR($F$1),INT((COLUMNS($F3:F3)-1)/4)+1,F$2*7-6))+1)
 
Upvote 0
Dear Mr. Haseeb,

Your sheet is having lot of loop holes. For example, For all Year column you are referring to Cell F11, if i am changing its month then your sheet is not working.

Check it and explain me Mr. Haseeb.

Regards,
Sathish Justin
 
Upvote 0
Assume your First row F1:AX1 is the 1st day of each month. 1/1/2010, 2/1/2010, 3/1/2010 & formatted as mmm-yy.

F3, copy down & across.

=($C3/($E3-$D3+1))*MAX(0,MIN($E3,LOOKUP(1E+100,1/($F$1:F$1),$F$1:F$1)+(F$2*7-1)+((F$2=4)*LOOKUP(DAY(EOMONTH(LOOKUP(1E+100,1/($F$1:F$1),$F$1:F$1),0)),{0,0;28,0;29,1;30,2;31,3})))-MAX(0,$D3,LOOKUP(1E+100,1/($F$1:F$1),$F$1:F$1)+(F$2*7-7))+1)
 
Upvote 0

Forum statistics

Threads
1,224,518
Messages
6,179,261
Members
452,901
Latest member
LisaGo

We've detected that you are using an adblocker.

We have a great community of people providing Excel help here, but the hosting costs are enormous. You can help keep this site running by allowing ads on MrExcel.com.
Allow Ads at MrExcel

Which adblocker are you using?

Disable AdBlock

Follow these easy steps to disable AdBlock

1)Click on the icon in the browser’s toolbar.
2)Click on the icon in the browser’s toolbar.
2)Click on the "Pause on this site" option.
Go back

Disable AdBlock Plus

Follow these easy steps to disable AdBlock Plus

1)Click on the icon in the browser’s toolbar.
2)Click on the toggle to disable it for "mrexcel.com".
Go back

Disable uBlock Origin

Follow these easy steps to disable uBlock Origin

1)Click on the icon in the browser’s toolbar.
2)Click on the "Power" button.
3)Click on the "Refresh" button.
Go back

Disable uBlock

Follow these easy steps to disable uBlock

1)Click on the icon in the browser’s toolbar.
2)Click on the "Power" button.
3)Click on the "Refresh" button.
Go back
Back
Top