Hi All,
I'm wondering if the below scenario is possible?
So let's say I have the following data
In the example above I want to track my target to date. Now if we look at it ourselves we know currently we are 100% to date. But when I ask excel to do a SUMIFS I have to state the range I want to calculate the sums which means the data is taking a total sum of the target and measuring it against the actual.
The question is, is there a way to as it to only measure if on a target to date RAG status that we are in fact 100% and green and not red(because the calculation thinks were only 10% target to date?
I'm wondering if the below scenario is possible?
So let's say I have the following data
Month | Month 2 | Month 3 | Month 4 | Month 5 | Month 6 | Month 7 | Month 8 | Month 9 | Month 10 | |||
Target | 100,000 |
| 100,000 | 100,000 | 100,000 | 100,000 | 100,000 | 100,000 | 100,000 | |||
Actual | 100,000 |
In the example above I want to track my target to date. Now if we look at it ourselves we know currently we are 100% to date. But when I ask excel to do a SUMIFS I have to state the range I want to calculate the sums which means the data is taking a total sum of the target and measuring it against the actual.
The question is, is there a way to as it to only measure if on a target to date RAG status that we are in fact 100% and green and not red(because the calculation thinks were only 10% target to date?