I have a workbook that calculates turnaround time. So, the project starts on 01/01/2011(cell H8), and finishes on 02/15/2011(cell AO8). I use the function "=NETWORKDAYS(H8,AO8)-1" and it gives me the number of days. Seems to work great.
Well, now we need to estimate the project completion date, based off the number of workdays in between. So, a series of cells calculate how many days the project should take (cell L8), and once we put in the project start date (cell H8), we want it to calculate, based off workdays, the estimated completion date.
Any ideas?
Well, now we need to estimate the project completion date, based off the number of workdays in between. So, a series of cells calculate how many days the project should take (cell L8), and once we put in the project start date (cell H8), we want it to calculate, based off workdays, the estimated completion date.