Building out a project plan trying to pull in predecessor dates to the successor. I wrote a formula to count the "." in the task #. I wanted to pull the max end date of the successors of the predecessors. So for 1.9's end date would like to receive the end date for 1.9.1. The issue I face is writing something that looks at them in sections and not pull in the dates of the next set of successors tied to another predecessor. Any help? preferred not to write any VBA

#TaskLeadSuccessor>1StartEndDays% complete
1.8Training for Information Steward for MDM teamKris1 - 00%
1.9Compile findings to Identify what data meets that criteriaSonia1 - 00%
1.9.1Create rules in " Information Steward"Sonia2 - 00%
1.10Excute the Information Steward data profilingSonia1 - 00%
1.11Business reviews the output of the profiled data and identifies the cleansing tasks Data Steward1 - 00%
1.12Develop an plan to terminate drivers: Sonia1 - 00%
1.12.1Request to IT/Business cleanse the data Sonia2 - 00%
1.12.2Testing on QA2 Sonia2 - 00%
1.12.3Move to productionSonia2 - 00%
1.13Perform QA the Information Steward profiling, validate resultsSonia1 - 00%
1.14Continuation of data cleansing:Sonia1 - 00%
1.14.1Business requests to terminate Sonia2 - 00%
1.14.2Develops program to terminate in all places, not just FM (or build pgm earlier in step so the business can clean their own data) Sonia2 - 00%

<colgroup><col><col><col><col><col><col><col><col></colgroup><tbody>
</tbody>
 

Excel Facts

What did Pito Salas invent?
Pito Salas, working for Lotus, popularized what would become to be pivot tables. It was released as Lotus Improv in 1989.
Hey there, I was having trouble understanding what exactly you are requesting. I'm not sure what predecessor date you are referring to. Can you explain it differrently and possibly show what you want it to show when it's working correctly
 
Upvote 0
I do not have end dates added yet but it would be added to the sheets.

Looking at 1.12 Develop a plan to terminate drivers, I would like to have it look at all the successors below, 1.12.1 - 1.12.3 and pull the max end date to the end date of 1.12 but not the dates for 1.13 or 1.14 and their successors of 1.14.1 & 1.14.2. Hope that makes more sense.
 
Upvote 0

Forum statistics

Threads
1,214,784
Messages
6,121,536
Members
449,037
Latest member
tmmotairi

We've detected that you are using an adblocker.

We have a great community of people providing Excel help here, but the hosting costs are enormous. You can help keep this site running by allowing ads on MrExcel.com.
Allow Ads at MrExcel

Which adblocker are you using?

Disable AdBlock

Follow these easy steps to disable AdBlock

1)Click on the icon in the browser’s toolbar.
2)Click on the icon in the browser’s toolbar.
2)Click on the "Pause on this site" option.
Go back

Disable AdBlock Plus

Follow these easy steps to disable AdBlock Plus

1)Click on the icon in the browser’s toolbar.
2)Click on the toggle to disable it for "mrexcel.com".
Go back

Disable uBlock Origin

Follow these easy steps to disable uBlock Origin

1)Click on the icon in the browser’s toolbar.
2)Click on the "Power" button.
3)Click on the "Refresh" button.
Go back

Disable uBlock

Follow these easy steps to disable uBlock

1)Click on the icon in the browser’s toolbar.
2)Click on the "Power" button.
3)Click on the "Refresh" button.
Go back
Back
Top