I am looking for an excel formula to identify the latest stage of a project.
<tbody>
</tbody>
Table shows progress for each project. I need a formula to calculate the stage (shaded green) at any time and for future projects to be added to the program.
For example, if project in row 3 has a date under 60%, then the Stage should change to 60%
Also, if two stages have the same date, it needs to show the stage furthest right
Thanks for any help offered.
A | B | C | D | E | F | G | H | I | J | |
1 | Progress Stages | |||||||||
2 | Project | Prepare | Start | 30% | 60% | 90% | Complete | Stage | ||
3 | Battersby | 21/09/2018 | 22/09/2018 | 15/12/2018 | 30% | |||||
4 | Phillips | 14/07/2018 | 20/07/2018 | 25/08/2018 | 25/11/2018 | 29/12/2018 | 90% | |||
5 | Jordsan | 09/07/2018 | 15/07/2018 | 20/08/2018 | 20/11/2018 | 24/12/2018 | 13/01/2019 | Complete | ||
6 | ||||||||||
7 |
<tbody>
</tbody>
Table shows progress for each project. I need a formula to calculate the stage (shaded green) at any time and for future projects to be added to the program.
For example, if project in row 3 has a date under 60%, then the Stage should change to 60%
Also, if two stages have the same date, it needs to show the stage furthest right
Thanks for any help offered.