Hi there, I am new to the forum.
i am trying to complete a spreadsheet for work area.
we have a date field with a process field then a pre process field ( this process usually takes place one or two days before the process.)
date field is ok
Process field is picked from a lookup list.
dependant on the process picked, I can use a vlookup to pull the pre-processes.
i want this formula to be in a hidden column and to populate the relevant pre-process field two days previous on the spreadsheet. I am unsure how to transfer the value into a cell reference of say G10-2 ie G8
i might have a process that requires a pre-process of three days previous so can't use a direct reference.
hope this is all clear.
i am trying to complete a spreadsheet for work area.
we have a date field with a process field then a pre process field ( this process usually takes place one or two days before the process.)
date field is ok
Process field is picked from a lookup list.
dependant on the process picked, I can use a vlookup to pull the pre-processes.
i want this formula to be in a hidden column and to populate the relevant pre-process field two days previous on the spreadsheet. I am unsure how to transfer the value into a cell reference of say G10-2 ie G8
i might have a process that requires a pre-process of three days previous so can't use a direct reference.
hope this is all clear.