Hi All
Looking for some help from you good people.
I have a workbook with two sheets. Sheet 1 is labeled Summary and Sheet 2 is labeled Detail.
Hoping to have Column R on Summary sheet to be update based on data found on the Detail sheet.
The logic I am trying to create would be If Column A on Detail Sheet matches Column B on Summary sheet and all of column G is "Complete" then Column R on Summary would show "Complete", If all of column G shows "On Hold" then Column R on summary would show "On Hold", If just one row in Column G shows "Not Started" then Column R on Summary would show "Not Started" and if just one row in Column G shows "In Progress" then Column R on Summary would show "In Progress"
Detail sheet below
A B C D E F G H
Example below
B8 on Summary shows Project F / A2 - A8 on Detail show Project "F" and G2 - G8 show "Complete" so R8 on Summary sheet should show "Complete"
Looking for some help from you good people.
I have a workbook with two sheets. Sheet 1 is labeled Summary and Sheet 2 is labeled Detail.
Hoping to have Column R on Summary sheet to be update based on data found on the Detail sheet.
The logic I am trying to create would be If Column A on Detail Sheet matches Column B on Summary sheet and all of column G is "Complete" then Column R on Summary would show "Complete", If all of column G shows "On Hold" then Column R on summary would show "On Hold", If just one row in Column G shows "Not Started" then Column R on Summary would show "Not Started" and if just one row in Column G shows "In Progress" then Column R on Summary would show "In Progress"
Detail sheet below
A B C D E F G H
Project | Associate | Role | Site | Function | Estimated Time per Week | Status | % Complete |
F | E | Project Lead | I | TP | 1 | Complete | 10 |
F | R | Involved | L | TP | 2 | Complete | 20 |
F | D | Involved | L | TP | 3 | Complete | 30 |
F | M | Involved | H | TP | 4 | Complete | 40 |
F | C | Involved | H | TP | 5 | Complete | 50 |
F | T | Involved | H | TP | 6 | Complete | 60 |
F | TY | Involved | H | TP | 7 | Complete | 70 |
F | R | Involved | N | TP | 8 | Complete | 80 |
Not F | E | Project Lead | I | TP | 1 | Complete | 10 |
Not F | R | Involved | L | TP | 2 | Not Started | 20 |
Not F | D | Involved | L | TP | 3 | Complete | 30 |
Not F | M | Involved | H | TP | 4 | Complete | 40 |
Not F | C | Involved | H | TP | 5 | Complete | 50 |
Not F | T | Involved | H | TP | 6 | Complete | 60 |
Not F | TY | Involved | H | TP | 7 | Complete | 70 |
Not F | R | Involved | N | TP | 8 | Complete | 80 |
Example below
B8 on Summary shows Project F / A2 - A8 on Detail show Project "F" and G2 - G8 show "Complete" so R8 on Summary sheet should show "Complete"