Is any one else having this problem...
I've tried several ways (never had a problem before) here is what I get:
1) WORKDAY(day(15),-1,holidays) Reutrning: 13
2) WORKDAY(DATE(2011,8,15),-1,holidays) Returning: 4/17/2101
Is any one having errors today? I have to use -2 in example 1 to get 12, the second one should work and it doesnt at all....?
Matt
I've tried several ways (never had a problem before) here is what I get:
1) WORKDAY(day(15),-1,holidays) Reutrning: 13
2) WORKDAY(DATE(2011,8,15),-1,holidays) Returning: 4/17/2101
Is any one having errors today? I have to use -2 in example 1 to get 12, the second one should work and it doesnt at all....?
Matt