Hi
I have table like below. The start date of Task2 is the End date of task1 +1
So B3 = D2 +1
But I want to avoid the date to be Saturday or sunday! So how can I do that so the start date of task2 wont be sat or sunday. Thank you so much.
<colgroup><col span="3"><col></colgroup><tbody>
</tbody>
I have table like below. The start date of Task2 is the End date of task1 +1
So B3 = D2 +1
But I want to avoid the date to be Saturday or sunday! So how can I do that so the start date of task2 wont be sat or sunday. Thank you so much.
task | start date | # of day | end date |
task1 | 2/27/2019 | 4 | =WORKDAY(B2,C2) |
task2 | =D2+1 | ||
task3 | |||
task4 | |||
task5 | |||
task6 | |||
task7 | |||
task8 |