Thread: Calculate a future date, excluding weekends.

  1. #1
    Guest

    Default

    If a project takes 25 days and starts today, what is the formula to predict the date the work is complete where there is a typical 5 day, Mon-Fri workweek?

    thanks

  2. #2
    MrExcel MVP Aladin Akyurek's Avatar
    Join Date
    Feb 2002
    Location
    The Hague, NL
    Posts
    83,660
    Post Thanks / Like
    Mentioned
    33 Post(s)
    Tagged
    6 Thread(s)

    Default

    On 2002-03-07 10:49, Anonymous wrote:
    If a project takes 25 days and starts today, what is the formula to predict the date the work is complete where there is a typical 5 day, Mon-Fri workweek?

    thanks
    =WORKDAY(A1,25)

    or

    =WORKDAY(A1,25,HOLIDAYS)

    where A1 houses a start date (e.g., today) and HOLIDAYS (in the second formula) is a range where you put known holiday dates, so you can exclude them to in determing the fure date.

    The function WORKDAY requires that the Analysis Toolpak is activated (via Tools|Add-Ins).


Some videos you may like

User Tag List

Like this thread? Share it with others

Like this thread? Share it with others

Posting Permissions

  • You may not post new threads
  • You may not post replies
  • You may not post attachments
  • You may not edit your posts
  •