    In F1 I need a formula that will look at the date in E1 and if the date is any date in Jan, then put in column F a 1, if it is a February date, then put in column F a 2, and so on.

    Can someone tell me how to do this?

    Thanks
    Terry

  2. #2
    MrExcel MVP
    Join Date
    Feb 2002
    Location
    Austin, Texas USA
    Posts
    11,654
    Post Thanks / Like
    Mentioned
    0 Post(s)
    Tagged
    0 Thread(s)

    Default

    No IF is required. Use...

    =MONTH(E1)

  3. #3
    MrExcel MVP Aladin Akyurek's Avatar
    Join Date
    Feb 2002
    Location
    The Hague, NL
    Posts
    83,644
    Post Thanks / Like
    Mentioned
    33 Post(s)
    Tagged
    6 Thread(s)

    Default

    On 2002-04-05 08:22, TClark14 wrote:
    In F1 I need a formula that will look at the date in E1 and if the date is any date in Jan, then put in column F a 1, if it is a February date, then put in column F a 2, and so on.

    Can someone tell me how to do this?

    Thanks
    Terry
    In F1 enter & copy down:

    =MONTH(E1)


  4. #4
    New Member
    Join Date
    Apr 2002
    Posts
    9
    Post Thanks / Like
    Mentioned
    0 Post(s)
    Tagged
    0 Thread(s)

    Default

    Thanks - I always think must be more complicated than they really are. So easy I never would have figured it out. Thanks Again.

Some videos you may like

User Tag List

Like this thread? Share it with others

Like this thread? Share it with others

Posting Permissions

  • You may not post new threads
  • You may not post replies
  • You may not post attachments
  • You may not edit your posts
  •