Removing Saturday and Sunday from five day intervals

G

Guest

Guest
Help.

I am tasked with calculating five working day intervals for start and end times, not including weekends.

The start date may be a Monday, with the job due on a Friday - easy - five days total.

The problem is when I get a start day on a Tuesday and then the finish day on the next Monday (the weekend days are included even though they don't really count as working days) the total days works out to seven (when in actual fact, the duration is five working days).

How can I set this up so that the weekend days are omitted in my query?
 

Excel Facts

Bring active cell back into view
Start at A1 and select to A9999 while writing a formula, you can't see A1 anymore. Press Ctrl+Backspace to bring active cell into view.

Forum statistics

Threads
1,214,945
Messages
6,122,393
Members
449,081
Latest member
JAMES KECULAH

We've detected that you are using an adblocker.

We have a great community of people providing Excel help here, but the hosting costs are enormous. You can help keep this site running by allowing ads on MrExcel.com.
Allow Ads at MrExcel

Which adblocker are you using?

Disable AdBlock

Follow these easy steps to disable AdBlock

1)Click on the icon in the browser’s toolbar.
2)Click on the icon in the browser’s toolbar.
2)Click on the "Pause on this site" option.
Go back

Disable AdBlock Plus

Follow these easy steps to disable AdBlock Plus

1)Click on the icon in the browser’s toolbar.
2)Click on the toggle to disable it for "mrexcel.com".
Go back

Disable uBlock Origin

Follow these easy steps to disable uBlock Origin

1)Click on the icon in the browser’s toolbar.
2)Click on the "Power" button.
3)Click on the "Refresh" button.
Go back

Disable uBlock

Follow these easy steps to disable uBlock

1)Click on the icon in the browser’s toolbar.
2)Click on the "Power" button.
3)Click on the "Refresh" button.
Go back
Back
Top