Hello,
I am trying to distribute predefined task hours evenly on working days (NETWORKDAYS) between 2 dates. I don't need to see the number of hours listed on each day, however, I do need to see the number of hours by month. Below is an example. I am looking for a formula to calculate the number of hours per month.
<colgroup><col width="72" style="width: 54pt; mso-width-source: userset; mso-width-alt: 2560;">
<col width="79" style="width: 59pt; mso-width-source: userset; mso-width-alt: 2816;" span="2">
<col width="75" style="width: 56pt; mso-width-source: userset; mso-width-alt: 2673;">
<col width="90" style="width: 68pt; mso-width-source: userset; mso-width-alt: 3214;">
<col width="77" style="width: 58pt; mso-width-source: userset; mso-width-alt: 2730;">
<col width="74" style="width: 56pt; mso-width-source: userset; mso-width-alt: 2645;">
<tbody>
</tbody>
Thank you!
I am trying to distribute predefined task hours evenly on working days (NETWORKDAYS) between 2 dates. I don't need to see the number of hours listed on each day, however, I do need to see the number of hours by month. Below is an example. I am looking for a formula to calculate the number of hours per month.
Start Date | End Date | Total Hours Required for Task | # of Work Days | Task Hours per Day | Nov. 2018 Hours | Dec. 2018 Hours |
29-Nov | 4-Dec | 5 | 4 | 1.25 | 2.5 | 2.5 |
Thank you!