Hello Excel Group!!!
This is my first post on this forum, seeking help.
I searched and went over many examples on this forum, none I could find which distributes over days.
I am trying to spread duration over the dates which fall between Start and Finish date of each task.
The "Start" & "Finish" date, can overlap last and first day of the month and month+1.
The "Work hours per day" is standard 8 hours, in some cases may be 4 hours (i.e. the task can be 4 hours or 8 hours).
Appreciate your help to resolve this problem, which I am trying to solve over 2 weeks now! Thanks in advance.
Here is the example in Xl2bb format:
This is my first post on this forum, seeking help.
I searched and went over many examples on this forum, none I could find which distributes over days.
I am trying to spread duration over the dates which fall between Start and Finish date of each task.
The "Start" & "Finish" date, can overlap last and first day of the month and month+1.
The "Work hours per day" is standard 8 hours, in some cases may be 4 hours (i.e. the task can be 4 hours or 8 hours).
Appreciate your help to resolve this problem, which I am trying to solve over 2 weeks now! Thanks in advance.
Here is the example in Xl2bb format:
Spread_Duration_Across_Days.xlsx | ||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
A | B | C | D | E | F | G | H | I | J | K | L | |||
1 | Example: | Weekend | ||||||||||||
2 | Name | Start | Finish | Duration | Work hours Per Day | 27-May-21 | 28-May-21 | 29-May-21 | 30-May-21 | 31-May-21 | 1-Jun-21 | 2-Jun-21 | ||
3 | John | 27-May-21 | 2-Jun-21 | 40 | 8 | 8 | 8 | 0 | 0 | 8 | 8 | 8 | ||
4 | Jack | 28-May-21 | 31-May-21 | 12 | 8 | 8 | 0 | 0 | 4 | |||||
5 | Jack | 31-May-21 | 2-Jun-21 | 20 | 8 | 0 | 0 | 4 | 8 | 8 | ||||
Sheet1 |
Cell Formulas | ||
---|---|---|
Range | Formula | |
G2:L2 | G2 | =F2+1 |