Hi! I have a task that takes 50 hours. it can start on any business day and runs 2 hours on Tuesdays and 2 hours on Wednesdays. I want to know the end date of the task.
Ex: if the start date is 03/22/2023, the end date will be 06/20/2023 excluding a holiday on Tuesday (holidays and vacation days can be in a column)
can someone give me a tip please