I am trying to set up a Spread sheet that will return 3 different values in the Date Status column (column G) based off of information on the spreadsheet.
Not Due - If the End Date column (Column F) date hasn't Passed
Overdue - If the End Date column (Column F) date has passed
Closed - If the End Date column (Column F) date has passed but the task status column (Column H) has been marked as "complete"
Any help with this would be great. Thanks!