Hi all,
Couldnt wrap my head around solving this issue today:
I want to calculate when to start producing a work order to meet a date. And the time it will take to build it, will have an index of hours.
Ex:
A date for the order to be ready is 2022-05-16
Time to build is 70 hours=8.75 days.
Now I need the date to find which date the order needs to start to meet deadline, excluding weekends since none is working then.
2022-05-16 minus 8,75 (9 working days) = 2022-05-03
Thanks!
Couldnt wrap my head around solving this issue today:
I want to calculate when to start producing a work order to meet a date. And the time it will take to build it, will have an index of hours.
Ex:
A date for the order to be ready is 2022-05-16
Time to build is 70 hours=8.75 days.
Now I need the date to find which date the order needs to start to meet deadline, excluding weekends since none is working then.
2022-05-16 minus 8,75 (9 working days) = 2022-05-03
Thanks!