nparsons75
Well-known Member
- Joined
- Sep 23, 2013
- Messages
- 1,254
- Office Version
- 2016
Hi,
I think this is a tricky one, it certainly is for me....
I need to display visually how well a project is running based on some date and percentage values.
<tbody>
</tbody>
So, in my table the % expected value is suggesting that the project should be 64% complete at the current date (today, 22/08/17).
We are actually only at 50% completion therefore the visual shows an AMBER COLORED cell. To achieve this I would like to have tolerances or ranges. Example below.
If the Actual Progress is = or greater than 64% then the visual will be GREEN.
If the Actual Progress is < or within 10% of the % expected then the visual will be AMBER. (53% to 63% in this case)
If the Actual Progress is > 10% below the % expected then the visual will be RED.
I have tried using Icon sets but couldn't get them to work as needed.
Thanks in advance if anyone can solve this...
I think this is a tricky one, it certainly is for me....
I need to display visually how well a project is running based on some date and percentage values.
START DATE | TODAY DATE | DUE DATE | PROJECT AGE | PROJECT LENGTH | % EXPECTED | Actual Progress | Visual |
1/1/17 | 22/08/17 | 31/12/17 | 233 | 364 | 64% | 50% | AMBER |
<tbody>
</tbody>
So, in my table the % expected value is suggesting that the project should be 64% complete at the current date (today, 22/08/17).
We are actually only at 50% completion therefore the visual shows an AMBER COLORED cell. To achieve this I would like to have tolerances or ranges. Example below.
If the Actual Progress is = or greater than 64% then the visual will be GREEN.
If the Actual Progress is < or within 10% of the % expected then the visual will be AMBER. (53% to 63% in this case)
If the Actual Progress is > 10% below the % expected then the visual will be RED.
I have tried using Icon sets but couldn't get them to work as needed.
Thanks in advance if anyone can solve this...